Road Projects

 

Description Start Date Stop Date Status

Multiple storm sewer drains have severe damage due to going years without any regular maintenance.  In October 2017 a resolution of necessity was passed by the SID #5 board that permits the issuance of bonds to repair the damage.

Currently there are 8 locations that will be repaired under this resolution of necessity.

This work will start in November of 2017 and continue until July 2018.

 

Spring 2018

Sep 2018

In Work

The roads thorughout the District are in need of significant repair.  In October 2017 a resolution of necessity was passed by the SID #5 board that permits the issuance of bonds to repair the damage.

Roads throughout the District will be repaired under this resolution of necessity.

This work will start in November of 2017 and continue until July 2018.  The work from November 2017 to early March 2018 will consist of additional planning and analysis.   

Spring 2018  Sep 2018  In Work