Road Projects

 

Description Start Date Stop Date Status

Multiple storm sewer drains have severe damage due to going years without any regular maintenance.  In October 2017 a resolution of necessity was passed by the SID #5 board that permits the issuance of bonds to repair the damage.

Currently there are 8 locations that will be repaired under this resolution of necessity.

This work will start in November of 2017 and continue until July 2018.

 

Spring 2018 Jul 2018 In Work

The roads thorughout the District are in need of significant repair.  In October 2017 a resolution of necessity was passed by the SID #5 board that permits the issuance of bonds to repair the damage.

Roads throughout the District will be repaired under this resolution of necessity.

This work will start in November of 2017 and continue until July 2018.  The work from November 2017 to early March 2018 will consist of additional planning and analysis.   

Spring 2018  Jul 2018  In Work

 

Tentative Schedule - 30 April 2018

  • Davy Jones Cir
    • 30 April - 2 May - Asphalt base repair
    • 7 May - Mill Surface
    • 9 May - Asphalt overlay - ROAD INACCESSIBLE 9:00AM - 4:30PM
  • Ridgeway
    • 30 April - Finish east side curb replacement.
    • 3 - 4 May - West side curb replacement.
    • 17 May - Mill Surface
    • 18 May - Asphalt overlay - ROAD INACCESSIBLE 9:00AM - 4:30PM
  • Windward
    • 1 - 2 May - Remove pavement/construct curb
    • 8 May -  Asphalt edging and pipe crossing pavement          
  • Fountain Circle
    • 7 - 8 May - Asphalt base repair
    • Curb repair to start as soon as finished at Windward

The plan moving forward at the east end will be to do one side of the cul-de-sacs, then move to the next cul-de-sac and do one side, then move to the next and do one side in order to get a week's cure.  Then return and do the other side in the same order.  After we finish Ridgeway we will prepare a more defined schedule for the east end.

Residents will be receiving letters prior to work staring on their road.